Cost Type | Requested Funding |
---|
Acquisition Cost | |
Building & Built-in Equipment | $107,732,412 |
Sitework & Utility Construction | |
Construction Cost Total | $107,732,412 |
DESIGN & RELATED SERVICE ITEMS | |
A/E Basic Services | $17,251,283 |
A/E Reimbursables | $341,254 |
Specialty Consultants (Food Service, Acoustics, etc.) | $417,115 |
CM Design Phase Services | $85,313 |
Subsurface Investigations (Geotech, Soil Borings) | $85,313 |
Land Survey | $106,926 |
Hazmat Survey & Design | $5,005 |
Other Design & Related Services | $942,185 |
Design & Related Services Total | $19,234,394 |
INSPECTION & TESTING SERVICE ITEMS | |
Project Inspection Services (inhouse or consultant) | $634,238 |
Project Testing Services (conc., steel, roofing, etc.) | $887,934 |
Inspection & Testing Services Total | $1,522,172 |
PROJECT MANAGEMENT & OTHER COST ITEMS | |
Project Management (inhouse or consultant) | $1,902,715 |
Work By Owner | $1,615,986 |
BCOM Services | $507,391 |
Advertisements | $1,820 |
Printing & Reproduction | $17,063 |
A/V Cabling | $2,292,998 |
Signage | $288,450 |
Demolition | $115,699 |
Hazardous Material Abatement | $34,506 |
Utility Connection Fees | $125,126 |
Utility Relocations | |
Commissioning | $343,950 |
Miscellaneous Other Costs | $6,184,152 |
Project Management & Other Costs Total | $13,429,856 |
Furnishings & Movable Equipment | $7,962,588 |
Construction Contingency | $2,154,648 |
TOTAL PROJECT COST | $152,036,070 |